 May
2008 - Work already is well under way to excavate a basement for the
new building. The basement will be used for mechanical space, storage
and some student organization offices.
|
 May 2008
-- Another view showing the basement excavation, with Old Main in the
background.
|
 May 30,
2008 -- Excavation work continues on the site of the new student center,
which is immediately in front of Rothwell Student Center, seen here in
the background.
|
|
 June
9, 2008 - Foundation footings for the student center begin to take
shape, and workers prepare more forms for the next pouring of concrete. |
 June
18, 2008 - The building's foundation and basement continues to take
shape. Workers at far left and far right are installing steel
reinforcement bars that will become part of the building's concrete
foundation.
|
 July
7, 2008 - Workers install concrete forms and reinforcement bar in
preparation for pouring the concrete basement walls. A completed portion
of the wall can be seen at far left.
|
|
 July
14, 2008 - The concrete basement walls continue to take shape.
|
 July
22, 2008 - Foundation work continues to progress.
|
 July
28, 2008 -- Forms go up for the remaining portion of the foundation
wall.
|
|
 Aug.
14, 2008 - This view shows the completed concrete basement of the
building's east end. Beyond that is the footprint for the remainder of
the building. |
 Aug.
20, 2008 -- Work on the foundation extends to the west while workers
in the basement prepare the ground for pouring the concrete floor. |
 Aug.
20, 2008 - This is how the building site appears from ground level
to someone looking from Barstow Hall toward Rothwell Student Center. |
|
 Aug.
27, 2008 - The basement floor has been poured (foreground) and the
foundation of the remainder of the building (background) is nearly
finished being poured. |
 Sept.
3, 2008 - Foundation work continues as fall semester begins.
|
 Sept.
10, 2008 - Masons build cement block walls inside the basement while
in the background, the curved front of the building takes shape. |
|
 Sept.
17, 2008 -- Masons are completing the concrete block interior walls
inside the basement (left side of the photo). In the background you can
see workers are compacting soil in preparation for pouring the concrete
for the
building's main floor. |
 Sept.
24, 2008 -- Following a day of heavy rain, everyone is busy. At
left, ironworkers are erecting structural steel while in the background
more concrete is being pouried.
|
 Sept.
24, 2008 -- A closer view of the first structural steel being
erected for the student center's shell.
|
|
 Sept.
25, 2008 -- What a difference a day makes! Workers are quickly
erecting the building's steel skeleton. Compare this photo to the
previous photo taken 24 hours earlier.
|
 Sept.
25, 2008 -- A crane lifts a girder into place in the frame of the
new student center.
|
 Sept.
25, 2008 -- Workers fasten a girder in place on the new student
center.
|
|
 Oct.
3, 2008 -- Ironworkers continue to erect the building's steel frame.
To the right in this view, concrete work and site preparation continue.
More girders remain on the site waiting to be put in place, and more
steel is being fabricated for the project.
|
 Oct.
8, 2008 -- Ironworkers add another girder to the frame of the
student center. To the right in this photo, you can see more girders
have been added across the site.
|
 Oct.
15, 2008 -- The building's steel frame continues to grow. Steel
flooring, visible at lower left, is being installed over the basement
areas. Out of sight to the right, a concrete entryway has been built.
|
|
 Oct.
29, 2008 -- A significant portion of the steel frame has been
erected. At left, workers have poured concrete over the steel
sub-flooring on the first floor and installed steel sub-flooring on the
second floor and steel roofing for the outdoor area at far left. In the center, workers are
building a concrete block shaft to house an elevator. The building
is expected to be enclosed by the end of December.
|
 Nov.
5, 2008 -- Earlier this week trucks began delivering roof trusses to
the site. Some already have been installed in this section of the
building. The concrete block structure is a stair well..
|
 Nov.
5, 2008 -- The photo, taken from Barstow Hall, shows the curving
front of the student center that will face Old Main. The large, slanted
beams will support the sloping "green roof" that will absorb rainwater
and deliver any excess to a small garden.
|
|
 Nov.
11, 2008 -- Although structural steel remains to be erected,
emphasis is now shifting to masonry work. Loads of concrete blocks are
arriving on the site. Workers are beginning to erect scaffolding around
this part of the building so they can begin to enclose it with masonry.
|
 Nov.
11, 2008 -- Workers have enclosed this area in plastic so they can
build an internal masonry wall under climate-controlled conditions.
Structural steel eventually will be erected around the area of the
building. |
 Nov.
19, 2008 -- Workers this week resumed erecting structural
steel and continued building masonry walls. This view shows the steel
sub-flooring that's been installed on the second floor.
|
|
 Nov.
19, 2008 -- On the north side of the building, work is proceeding on
erecting the last of the structural steel and building an interior
masonry wall.
|
|
|
|