Posted on Jul 11, 2013
Campus construction continues with more road closing alerts:
click to enlarge
Campus construction update:  new road closing

An extensive campus steam line repair/replacement summer project continues.

Currently the contactor has Catlin Ave closed between 16th and 19th streets due to trenching across Catlin Ave. You can get around campus be utilizing the bordering streets (16th, Weeks, 19th and Mortorelli Dr).

However, the latest road closure, as of July 11, is at Catlin Ave. and Faxon street (near Hawkes Hall). It is advisable to use Lamborn Ave. to get between 28th Street and 21st street. Please follow all contractor posted detour signs for best routing.

This project consists of excavating portions of existing underground campus steam lines damaged by the June 2012 campus flood. This project is necessary to correct damaged pipe and insulation due to the steam line vaults being totally flooded during the June flood. To complete the project additional steam lines will be repaired in two phases: summer of 2013 and summer of 2014. These repairs will result in increased longevity, higher grade insulation, waterproofing and increased energy efficiencies.

Project Locations
There will be three (3) main campus locations for this project.
1. Steam line replacement from the Halbert heating plant west along Faxon Street to the southwest corner of Faxon St. and Catlin Ave (Hawkes Hall)

2. Steam line repair from the west side of Marcovich Wellness Center (MWC) across Catlin Ave to Holden Fine Arts Center (HFAC), along the north side of HFAC toward the Jim Dan Hill Library

3. Steam line repairs from the front of Crownhart Hall south along Catlin Ave, west across Catlin Ave to Barstow HallRoad and Sidewalk Closures

This project will create three (3) road closures along Catlin Ave at certain points of construction. One will be between Crownhart and CMO, a second will be between MWC and HFAC, and the third will be at the intersection of Catlin Ave and Faxon Street near Hawkes Hall.

These closures will provide detour routes for vehicles. Some limitations will be set on these closures to accommodate school bus traffic and other peak vehicle times. The Duluth Transit Authority will temporarily reroute Catlin Ave bus traffic during construction and will publish alternate routes.

Several sidewalks will be closed to pedestrian traffic in and near the construction sites. Alternative pedestrian routes will be open to allow access to all campus buildings.

Safety:


The contactors will be securing the construction sites with fencing, barricades and signage. Please use extreme caution when traveling around these areas either by vehicle or on foot. Safety is all of our responsibility; don't always rely on others. On behalf of the campus, your understanding and patience during the much needed project is very much appreciated.

Please use caution when walking or driving near the work zones as trucks and heavy equipment will be in use entering and exiting the work sites.

Work will continue through the end of August with substantial completion before Fall Semester. Some sod and seeding may occur at the beginning of the Semester, but all of the repairs and dirt work will be completed.

Please find a campus map showing the construction routes and detour points at the following web site: http://www.uwsuper.edu/facilities/loader.cfm?csModule=security/getfile&PageID=1491484

News Contact: Tom Hansen | 715-394-8260 | thansen7{atuws}